Decision Memo Completed

Shantytown Telephone/Powerline Relocation Project

Humboldt-Toiyabe National Forest Elko, Nevada Mountain City Ranger District

Construction of a new telephone/powerline, approximately 800 feet in length to provide continued service to the residences in Shantytown.

Location

Shantytown on east side of Ruby Mountains

Project timeline

1
Scoping Start
04/22/2019
2
Decision
05/2019 (Estimated)
3
Implementation
06/2019 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Shantytown Telephone/Powerline Relocation ProjectDecision Signed Date: 05/30/2019
ForestsHumboldt-Toiyabe National Forest
DistrictsMountain City Ranger District
Legal Land DescriptionNot Applicable
Special use management