Newcrest Resources proposes a 10 year minerals exploration project. Phase 1 of the project will include up to 22 drill sites, one temporary aquatic organism passage culvert, six miles of temporary road and 23.98 acres of surface disturbance.
Location
Near the town Jarbidge, NV
Project timeline
1
Scoping Start
11/25/2019
2
Comment Period
11/26/2019
3
Objection Period Start
04/09/2020
4
Decision
09/2020 (Estimated)
5
Implementation
09/2020 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Newcrest Jarbidge Exploration Project | Decision Signed Date: 09/11/2020 |
| Forests | Humboldt-Toiyabe National Forest |
| Districts | Jarbidge Ranger District |
| Legal Land Description | Not Applicable |