Rebuild approximately 9.23 mile, 60 kilovolt (kV) transmission line within the existing right-of-way between the Voltaire Substation in Carson City, Nevada and Glenbrook Substation, Douglas County, Nevada.
Location
West side of Carson City Nevada, from Voltaire Canyon heading west across U.S. Highway 50 to the intersection of Nevada State Route 28 and Spooner Summit, then parallels old Highway 50 to Glenbrook.
Project timeline
1
Scoping Start
04/10/2020
2
Decision
09/2021 (Estimated)
3
Implementation
03/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Carson City to Glenbrook Powerline Rebuild | Decision Signed Date: 09/12/2021 |
| Forests | Humboldt-Toiyabe National Forest; Lake Tahoe Basin Mgt Unit |
| Districts | Carson Ranger District; Lake Tahoe Basin Mgt Unit |
| Legal Land Description | Not Applicable |