The remediation plan is to consolidate the waste at each portion of the site and cover it with approximately two feet of soil, mounding as needed so surface water runs off. At UVC there will be a berm to direct surface water away from the mound.
Location
Both worksites are adjacent to State Highway 21 Near the intersection with NFS road 0218.
Project timeline
1
Scoping Start
08/30/2021
2
Decision
03/2022 (Estimated)
3
Implementation
05/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Harzardous Waste Compliance Actions; Watershed Improvements |
| Upper and Lower Virginia Creek Clean-up | Decision Signed Date: 03/03/2022 |
| Forests | Humboldt-Toiyabe National Forest |
| Districts | Bridgeport Ranger District |
| Legal Land Description | Not Applicable |