Decision Memo Cancelled

Moab Ditch Bill Easements - Upper La Sal Creek

Manti-La Sal National Forest San Juan, Utah Moab Ranger District

This project does not require a written decision (ie Decision Memo) and therefore was removed from the SOPA.

Location

La Sal Creek, North of Doe Creek

Project timeline

1
Scoping Start
09/24/2008
2
Decision
12/2012 (Estimated)
3
Implementation
04/2013 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (10)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsManti-Lasal National Forest
DistrictsMoab Ranger District
Legal Land DescriptionT28S, R25E, Section 7