Camp UTIBACA requests a special use permit to construct, operate, and maintain an underground electric cable in Willow Creek Road to the private camp.
Location
Willow Creek Road is located in Ephraim Canyon approximately five miles east of Ephraim, UT.
Project timeline
1
Scoping Start
02/15/2011
2
Decision
08/2011 (Estimated)
3
Implementation
09/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Camp UTIBACA Underground Electric Cable Special Use Permit | Decision Signed Date: 08/30/2011 |
| Forests | Manti-Lasal National Forest |
| Districts | Sanpete Ranger District |
| Legal Land Description | Sections 19 and 30, T17S, R4E of the Salt Lake principal meridian. |