The San Juan Water Conservancy District and Blanding City are proposing to increase the size of the Dry Wash Reservoir and add a pipeline from the dam to the existing City pipeline.
Location
Approximately 10 miles north northwest of Blanding Utah.
Project timeline
1
Scoping Start
07/23/2013
2
Comment Period
07/23/2013
3
Objection Period Start
06/05/2014
4
Decision
07/2014 (Estimated)
5
Implementation
08/2014 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Dry Wash Reservoir Expansion and Pipeline | Decision Signed Date: 07/28/2014 Legal Notice Date: 07/28/2014 |
| Forests | Manti-Lasal National Forest |
| Districts | Monticello Ranger District |
| Legal Land Description | T34S R22E Sec. 31 |