Empire Electric is proposing to replace their existing aerial and buried powerline with a new buried line from a private inholding to the Abajo Peak Communication Site.
Location
Approximately 6 miles west southwest of Monticello Utah.
Project timeline
1
Scoping Start
06/2015 (Estimated)
2
Comment Period
07/2015 (Estimated)
3
Objection Period Start
10/2015 (Estimated)
4
Decision
12/2015 (Estimated)
5
Implementation
01/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Manti-Lasal National Forest |
| Districts | Monticello Ranger District |
| Legal Land Description | T34S R22E, Sec 1 & 12. T34S R23E, Sec 6. |