This proposed 500 kV transmission line is designed to deliver power to Rocky Mountain Power utility costumers in Utah and the intermountain west. Generation sources are located in central Wyoming.
Location
The project initiates in central Wyoming and crosses public, private, and state lands in Wyoming, Colorado, and Utah. Project terminates at the Mona substation in central Utah.
Project timeline
1
NOI in Federal Register
04/01/2011
2
DEIS NOA in Federal Register
04/01/2011
3
FEIS NOA in Federal Register
01/13/2017
4
Objection Period Start
01/21/2017
5
Decision
05/2017 (Estimated)
6
Implementation
01/2020 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Energy Gateway South Transmission Project | Decision Signed Date: 05/31/2017 |
| Forests | Ashley National Forest; Dixie National Forest; Fishlake National Forest; Manti-Lasal National Forest; Uinta-Wasatch-Cache National Forest |
| Districts | Duchesne Ranger District; Pine Valley Ranger District; Fillmore Ranger District; Richfield Ranger District; Price Ranger District; Heber-Kamas Ranger District; Spanish Fork Ranger District |
| Legal Land Description | Not Applicable |