The FS will analyze Emery telecom proposal to install a fiber optic telecommunications cable and facilities to upgrade services to an existing cell tower. Approximately 6.5 miles of cable would be placed on existing powerline poles across NFS lands.
Location
Bald Mesa Area
Project timeline
1
Scoping Start
07/01/2016
2
Decision
10/2016 (Estimated)
3
Implementation
11/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Emery Telecom - Bald Mesa | Decision Signed Date: 10/28/2016 |
| Forests | Manti-Lasal National Forest |
| Districts | Moab Ranger District |
| Legal Land Description | Not Applicable |