In accordance with Special Use Regulations, Forest Service review of a request to replace and bury an existing powerline and place a communication cable in the same trench.
Location
T. 34S, R.22E SE1/4NE1/4 of Section 6
Project timeline
1
Scoping Start
07/01/2016
2
Decision
09/2016 (Estimated)
3
Implementation
10/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Empire Electric Powerline Replacement and Emery Telcom Communications at Abajo Peak | Decision Signed Date: 09/19/2016 |
| Forests | Manti-Lasal National Forest |
| Districts | Moab Ranger District; Monticello Ranger District |
| Legal Land Description | Not Applicable |