The Forest proposes to issue a 30 yr SUP to UDOT Avalanche Forecasting program for the installation of a weather station on the existing Monument Peak Communication Site to assist avalanche forecasters in the collection of data for hazard evaluation.
Location
The existing Monument Peak Communication Site near Trough Springs Ridge.
Project timeline
1
Scoping Start
09/01/2016
2
Decision
09/2016 (Estimated)
3
Implementation
10/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| UDOT Monument Peak Weather Station Special Use Permit | Decision Signed Date: 09/26/2016 |
| Forests | Manti-Lasal National Forest |
| Districts | Ferron Ranger District; Price Ranger District |
| Legal Land Description | Not Applicable |