Installation of a spring head box, 2500-foot pipeline, and a trough to provide water to livestock in 2 pastures (East & West McCadden) of the Gentry Allotment.
Location
Gentry C&H Allotment
Project timeline
1
Scoping Start
04/25/2017
2
Decision
09/2018 (Estimated)
3
Implementation
10/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| McCadden Hollow Water Trough Project | Decision Signed Date: 09/25/2018 |
| Forests | Manti-Lasal National Forest |
| Districts | Ferron Ranger District |
| Legal Land Description | T16S, R7E, Sec. 1, NE 1/4 of SW 1/4, SLM |