Decision Memo Completed

McCadden Hollow Water Trough Project

Manti-La Sal National Forest Emery, Utah Ferron Ranger District

Installation of a spring head box, 2500-foot pipeline, and a trough to provide water to livestock in 2 pastures (East & West McCadden) of the Gentry Allotment.

Location

Gentry C&H Allotment

Project timeline

1
Scoping Start
04/25/2017
2
Decision
09/2018 (Estimated)
3
Implementation
10/2018 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (9), 36 Cfr 220.6(E)(9)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Structural Improvements
McCadden Hollow Water Trough ProjectDecision Signed Date: 09/25/2018
ForestsManti-Lasal National Forest
DistrictsFerron Ranger District
Legal Land DescriptionT16S, R7E, Sec. 1, NE 1/4 of SW 1/4, SLM
Grazing management