Authorization of Recreation Special Use Permits for Priority status for up to 5 years. Permittees include variety of outfitters/guide operations and recreation events on the districts.
Location
Moab and Monticello Ranger Districts of the Manti-La Sal National Forest Service
Project timeline
1
Scoping Start
11/14/2018
2
Decision
12/2018 (Estimated)
3
Implementation
02/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3); 32.12 (10); 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Renewal Priority Special Use Permits and Amemdments (Fall 2018) | Decision Signed Date: 12/19/2018 |
| Forests | Manti-Lasal National Forest |
| Districts | Moab Ranger District |
| Legal Land Description | Not Applicable |