Implement structural improvements designed to harden & improve, or restore temporary structures installed during BAER work following the Trail Mountain Fire (2018). Some new structures are proposed for additional protection.
Location
Meetinghouse Canyon, Rilda Canyon, and Mill Fork Canyon within the Huntington Creek Watershed.
Project timeline
1
Scoping Start
07/17/2019
2
Decision
10/2019 (Estimated)
3
Implementation
10/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (11), 36 Cfr 220.6(E)(11); 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | National Fire Plan - Healthy Forests Initiative Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Watershed Improvements |
| Trail Mountain Fire Emergency Watershed Protection Project | Decision Signed Date: 10/03/2019 |
| Forests | Manti-Lasal National Forest |
| Districts | Ferron Ranger District; Price Ranger District |
| Legal Land Description | Not Applicable |