The project is focused on four cultural sites within the Bears Ears National Monument. The project will involve designating and constructing access trails and parking areas, as well as installing signage
Location
Moab/Monticello Ranger District, Bears Ears National Monument
Project timeline
1
Scoping Start
01/06/2022
2
Comment Period
06/01/2022
3
Objection Period Start
07/27/2022
4
Decision
09/2022 (Estimated)
5
Implementation
09/2022 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Heritage Resource Management; Trail Management; Special Area Management |
| Cultural Site Visitor Management Project | Decision Signed Date: 09/22/2022 |
| Forests | Manti-Lasal National Forest |
| Districts | Monticello Ranger District |
| Legal Land Description | Not Applicable |