Emery Telcom is proposing to bury two approximately 6,200ft, HDPE conduit. Empire Electric is proposing to bury approximately 6,700ft of existing aerial powerline.
Location
Along FS Rd 50032 and 50034 to Blue Mountain Ranches
Project timeline
1
Scoping Start
11/22/2024
2
Decision
01/2025 (Estimated)
3
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Emery Telcom - Empire Electric Utility Project | Decision Signed Date: 01/15/2025 |
| Forests | Manti-Lasal National Forest |
| Districts | Monticello Ranger District |
| Legal Land Description | T34 S R23E Sec 28 & 32 |