Implement adaptive and integrated invasive plant management on current and potential infested areas which would include inventory and assessment designed to support Early Detection Rapid Response, control methods, monitoring, and rehabilitation.
Location
Salmon-Challis National Forest outside of the Frank Church-River of No Return Wilderness Area
Project timeline
1
NOI in Federal Register
06/23/2011
2
DEIS NOA in Federal Register
02/13/2015
3
FEIS NOA in Federal Register
11/13/2015
4
Objection Period Start
11/19/2015
5
Decision
07/2016 (Estimated)
6
Implementation
07/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Noxious Weed Treatments |
| Salmon-Challis National Forest Invasive Plant Treatment Final ROD | Decision Signed Date: 07/06/2016 |
| Forests | Salmon-Challis National Forest |
| Districts | Salmon-Challis National Forest All Units |
| Legal Land Description | Not Applicable |