The project will replace a 500 foot section of the Kane Creek Road #134 that has washed out. The project will eliminate resource damage associated with vehicle use at the washed out section of road while still maintaining access to the trailhead.
Location
Kane Creek approximately 3.6 miles south of Summit Creek and 28 miles west of Mackay, Idaho
Project timeline
1
Scoping Start
03/15/2012
2
Comment Period
04/12/2012
3
Decision
07/2012 (Estimated)
4
Implementation
09/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Improvements/Construction; Watershed Improvements |
| Kane Canyon Road Repair Decision Memo | Decision Signed Date: 07/13/2012 Legal Notice Date: 07/19/2012 |
| Forests | Salmon-Challis National Forest |
| Districts | Lost River Ranger District |
| Legal Land Description | T6N R19E section 23 |