Decision Memo Completed

Lost River Electric Permit Amendment to bury powerline to Windy Devil Communication Site

Salmon-Challis National Forest Custer, Idaho Salmon-Challis National Forest All Units

Bury existing overhead powerline within the ROW for approximately 1/2 mile on NFS land.

Location

Windy Devil Communication Site, 3 miles west of Mackay, ID.

Project timeline

1
Scoping Start
07/05/2012
2
Comment Period
07/15/2012
3
Decision
10/2012 (Estimated)
4
Implementation
10/2012 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityElectric Transmission
Amendment to Permit LSR71 to Bury Powerline and Fiber Optic CableDecision Signed Date: 10/09/2012
ForestsSalmon-Challis National Forest
DistrictsLost River Ranger District
Legal Land DescriptionT. 7 N., R. 23 E., section 24
Special use management