The project will increase forest stand resilience to insect, disease, and wildfire utilizing silvicultural practices such as mechanical thinning and prescribed fire.
Location
15 miles northwest of Stanley, ID along State Highway 21
Project timeline
1
Scoping Start
02/08/2017
2
Comment Period
02/08/2017
3
Decision
03/2018 (Estimated)
4
Implementation
06/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green) |
| South 21 Project | Decision Signed Date: 03/12/2018 |
| Forests | Salmon-Challis National Forest |
| Districts | Challis-Yankee Fork Ranger District |
| Legal Land Description | Portions of T12N, R10E (S25, 24, 13,), T12N, R11E (S36, 35, 34, 28, 27, 26, 25, 24, 23, 22, 21,16, 15, 14, 10, 9,), T12N, R12E (S 31, 30) Boise Meridian |