The proposed action is to reissue an expired special use permit for an existing 7.2 Kv power transmission line for a term of 30 years.
Location
The right of way is approximately 6.7 miles in length between the national forest boundary near Wallace Lake heading west to the Federal Aviation Administration%u2019s VOR/DME station at Lake Mountain.
Project timeline
1
Scoping Start
12/07/2016
2
Decision
02/2018 (Estimated)
3
Implementation
05/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Idaho Power Lake Mountain Power Transmission Line Special Use Permit Renewal | Decision Signed Date: 02/22/2018 |
| Forests | Salmon-Challis National Forest |
| Districts | Salmon-Cobalt Ranger District |
| Legal Land Description | Not Applicable |