Project timeline

1
Scoping Start
02/01/2018
2
Comment Period
02/01/2018
3
Objection Period Start
08/16/2018
4
Decision
09/2018 (Estimated)
5
Implementation
06/2019 (Estimated)

NEPA / regulatory detail

Special AuthorityHfra Title I: Wildland-Urban Interface; Hfra Title I: Municipal Watersheds
Notice and Comment Regulation218 (2013) HFRA
Project ActivityFuel Treatments (Non-Activity Fuels); Watershed Improvements
Salmon Municipal WatershedDecision Signed Date: 09/27/2018
Salmon Municipal Watershed RestorationDecision Signed Date: 09/27/2018
ForestsSalmon-Challis National Forest
DistrictsSalmon-Cobalt Ranger District
Legal Land DescriptionNot Applicable
Watershed managementFuels management