Install a 10,000 gallon water holding tank along the Gilmore pipeline near the water trough. Tank would be buried adjacent to the road above the trough.
Location
South of Leadore off Hwy 28, near Gilmore Summit on FS road #60251
Project timeline
1
Scoping Start
07/21/2020
2
Decision
08/2020 (Estimated)
3
Implementation
08/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Allotment Management; Grazing Structural Improvements |
| Gilmore Water Tank | Decision Signed Date: 08/19/2020 |
| Forests | Salmon-Challis National Forest |
| Districts | Leadore Ranger District |
| Legal Land Description | Not Applicable |