A variety of hazardous fuels reduction treatments over approximately 9,000 acres. Treatment types may include prescribed fire, hand thinning, and may also include commercial and non-commercial forest products.
Location
Bayhorse Watershed, near Challis, Idaho.
Project timeline
1
Scoping Start
10/14/2020
2
Comment Period
06/16/2022
3
Objection Period Start
04/06/2023
4
Decision
11/2023 (Estimated)
5
Implementation
01/2024 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Bayhorse ProjectV2 | Decision Signed Date: 11/06/2023 |
| Forests | Salmon-Challis National Forest |
| Districts | Challis-Yankee Fork Ranger District |
| Legal Land Description | Not Applicable |