Approve a plan to drill up to two holes per pad on four drill pads, use less than 1 mile of temporary closed user-created routes and less than 0.5 miles of overland travel for drill pad access, and draft water from Agency Creek.
Location
Lemhi Pass area approximately ten (10) air miles east of Tendoy, in Lemhi County, Idaho
Project timeline
1
Scoping Start
11/18/2020
2
Decision
05/2021 (Estimated)
3
Implementation
05/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Copper Queen Exploration Drilling | Decision Signed Date: 05/24/2021 |
| Forests | Salmon-Challis National Forest |
| Districts | Leadore Ranger District |
| Legal Land Description | Not Applicable |