The Operator proposes to disturb up to a total of 230 acres by constructing 24 miles of temporary roads, 300-400 drill sites, up to 4 drill holes per site and staging in phases spread across ten years.
Location
Sections 5, 8, 9, 10, 16, 20, 21, 28, 29, and 32 of Township 22 North, Range 20 East (T22N, R20E), Sections 13, 14, 15, 16, 21, 22, 23 and 24, of T22N, R19E, Section 5 and 6 of T21N, R20E, Boise Prime
Project timeline
1
Scoping Start
04/08/2021
2
Comment Period
04/08/2021
3
Objection Period Start
03/17/2022
4
Decision
08/2022 (Estimated)
5
Implementation
08/2022 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| BTAC Exploration Drilling Project | Decision Signed Date: 08/01/2022 |
| Forests | Salmon-Challis National Forest |
| Districts | Salmon-Cobalt Ranger District |
| Legal Land Description | Not Applicable |