This Plan of Operation includes: 1) trenching and 2) drilling and 3) road maintenance. Trenching: It is anticipated that 10 to 12 trenches may be excavated Drilling: Neuma proposes drilling a total of 10 to 15 diamond core holes
Location
7 miles SE of Salmon Idaho. Upper Mulkey Creek
Project timeline
1
Scoping Start
12/23/2021
2
Decision
07/2022 (Estimated)
3
Implementation
10/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Pope-Shenon drilling and trenching | Decision Signed Date: 07/06/2022 |
| Forests | Salmon-Challis National Forest |
| Districts | Salmon-Cobalt Ranger District |
| Legal Land Description | Not Applicable |