Construct a 1.25-mile pipeline on the Boone Creek Allotment consisting of a spring development (headbox) and approximately 1.25 miles of polyethylene pipe conveying water to five water troughs.
Location
North of the East Fork of the Big Lost River/ Copper Basin Road (1.4 miles). Between Castle Creek and Butcher Creek near Dry Canyon. 17 miles west of the City of Mackay, Idaho
Project timeline
1
Scoping Start
11/03/2022
2
Decision
03/2023 (Estimated)
3
Implementation
03/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Allotment Management; Grazing Structural Improvements |
| Castle Creek Range Improvement | Decision Signed Date: 03/30/2023 |
| Forests | Salmon-Challis National Forest |
| Districts | Lost River Ranger District |