The proposal is to treat about 4,000 acres within the 17,000 acre Big Creek watershed to implement the Revised Forest Plan and move towards properly functioning conditions across the landscape.
Location
Big Creek watershed about 50 miles east of Ogden, Utah
Project timeline
1
NOI in Federal Register
05/16/2006
2
DEIS NOA in Federal Register
07/20/2007
3
FEIS NOA in Federal Register
05/09/2008
4
Decision
04/2008 (Estimated)
5
Implementation
07/2008 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green) |
| Big Creek Vegetation Treatment Project | Decision Signed Date: 04/15/2008 Legal Notice Date: 05/01/2008 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Ogden Ranger District |