Brighton Properties/Silver Lake Estates #1 subdivision is proposing toreplace an existing 2 inch dia. galvanized steel water transmission line that supplies water from an existing spring box, to their 150,000 gal buried concrete storage tank.
Location
Brighton Loop, Big Cottonwood Canyon
Project timeline
1
Scoping Start
10/24/2008
2
Decision
07/2009 (Estimated)
3
Implementation
08/2009 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Salt Lake Ranger District |
| Legal Land Description | R3E, T2S, Sec. 35 |