Decision Memo Completed

Pleasant Grove Pipeline-Grove Creek Project

Uinta-Wasatch-Cache National Forest Utah, Utah Pleasant Grove Ranger District

The City of Pleasant Grove proposes to divert water from the Pleasant Grove Irrigation Company's existing pipeline, located at the Grove Creek Trailhead, into their existing irrigation system.

Location

Grove Creek Trailhead, Pleasant Grove, UT

Project timeline

1
Scoping Start
05/07/2010
2
Decision
05/2010 (Estimated)
3
Implementation
05/2010 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Pleasant Grove Pipeline-Grove Creek ProjectDecision Signed Date: 05/13/2010
ForestsUinta-Wasatch-Cache National Forest
DistrictsPleasant Grove Ranger District
Legal Land DescriptionT5S R2E, SW 1/4 Sec. 15, NW 1/4 Sec. 22 SLBM
Special use management