Proposal is to re-route about 1,000 feet of ATV trail to relocate it outside the fenced compund of the Elk Valley Guard Station. The guard station was fenced to keep livestock and traffic out of the compound.
Location
Just north of the Elk Valley Guard Station
Project timeline
1
Scoping Start
11/08/2012
2
Comment Period
11/08/2012
3
Decision
12/2012 (Estimated)
4
Implementation
07/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management |
| Elk Valley Trail Reroute Decision Memo | Decision Signed Date: 12/17/2012 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Logan Ranger District |
| Legal Land Description | T12N, R4E, Sections 33 and 34 |