It is proposed to harvest dead and infested Engelmann spruce within the 27 acres area of the Piuta Organizational Camp. No temporary roads are proposed.
Location
This project is located approximately 14 air miles east of Francis, Utah.
Project timeline
1
Scoping Start
11/20/2012
2
Comment Period
12/01/2012
3
Decision
05/2013 (Estimated)
4
Implementation
06/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Timber Sales (Salvage) |
| Piuta Hazard Tree Removal | Decision Signed Date: 05/02/2013 Legal Notice Date: 05/06/2013 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Heber-Kamas Ranger District |
| Legal Land Description | Township 2N, Range 8E, Section 21, SLBM |