The SFRD is proposing to re-issue a special use authorization for a 354 kV power transmission line, known as the Upalco to Mona Transmission line. Permit would be re-issued for 40-years.
Location
The project crossed for 19.21 miles in the Spanish Fork and Heber-Kamas Ranger District and 0.6 miles in the Manti-LaSal National Forest
Project timeline
1
Scoping Start
04/06/2013
2
Comment Period
04/06/2013
3
Decision
05/2013 (Estimated)
4
Implementation
07/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Deseret Power and Transmition Special Use Permit | Decision Signed Date: 05/07/2013 Legal Notice Date: 05/09/2013 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Spanish Fork Ranger District |