Questar is proposing to replace a section of its Feeder Line (FL) 24 natural gas pipeline near Highland, Utah.
Location
The project crosses land managed by U.S. Forest Service, Uinta-Wasatch-Cache National Forest, Pleasant Grove Ranger District near Highland, Utah (Utah County).
Project timeline
1
Scoping Start
06/27/2013
2
Comment Period
06/27/2013
3
Decision
08/2013 (Estimated)
4
Implementation
08/2014 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Questar Feeder Line 24 Highland, Utah Replacement Project | Decision Signed Date: 08/15/2013 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Pleasant Grove Ranger District |
| Legal Land Description | Not Applicable |