Environmental Impact Statement Completed

Energy Gateway South 500 kV Powerline (EGS)

Uinta-Wasatch-Cache National Forest Beaver; Duchesne; Emery; Garfield; Iron; Juab; Millard; Piute; Sevier; Uintah; Wasatch; Weber, Utah Uinta-Wasatch-Cache All Units

This proposed 500 kV transmission line is designed to deliver power to Rocky Mountain Power utility costumers in Utah and the intermountain west. Generation sources are located in central Wyoming.

Location

The project initiates in central Wyoming and crosses public, private, and state lands in Wyoming, Colorado, and Utah. Project terminates at the Mona substation in central Utah.

Project timeline

1
NOI in Federal Register
04/01/2011
2
DEIS NOA in Federal Register
04/01/2011
3
FEIS NOA in Federal Register
01/13/2017
4
Objection Period Start
01/21/2017
5
Decision
05/2017 (Estimated)
6
Implementation
01/2020 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations
Energy Gateway South Transmission ProjectDecision Signed Date: 05/31/2017
ForestsAshley National Forest; Dixie National Forest; Fishlake National Forest; Manti-Lasal National Forest; Uinta-Wasatch-Cache National Forest
DistrictsDuchesne Ranger District; Pine Valley Ranger District; Fillmore Ranger District; Richfield Ranger District; Price Ranger District; Heber-Kamas Ranger District; Spanish Fork Ranger District
Legal Land DescriptionNot Applicable
Special use management