The proposed action includes a 12-inch buried carbon steel pipeline approximately 135 miles long and ancillary facilities. Approximately 14 miles of the pipeline would be on the Uinta-Wasatch-Cache National Forest.
Location
The proposed pipeline would cross the UWCNF in the Wolf Creek/Upper South Fork Provo River area of the Heber-Kamas Ranger District, and in the Bountiful Peak area of the Salt Lake Ranger District.
Project timeline
1
NOI in Federal Register
01/22/2014
2
DEIS NOA in Federal Register
01/31/2014
3
FEIS NOA in Federal Register
06/2015 (Estimated)
4
Objection Period Start
08/2015 (Estimated)
5
Decision
03/2016 (Estimated)
6
Implementation
04/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Ira - Inventoried Roadless Area Activities Requiring Chief's Approval |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Salt Lake Ranger District; Heber-Kamas Ranger District |
| Legal Land Description | Not Applicable |