Decision Memo Completed

Rocky Mountain Power Structure Install, Replacement, Phase Raising

Uinta-Wasatch-Cache National Forest Weber, Utah Ogden Ranger District

Proponent proposes to do maintenance and install 3 new structures along the existing Naughton to Ben Lomond Power Line within their current right of way. The purpose of the project is to reduce slack in the line.

Location

Two sites approximately 8 miles and 25 miles northeast of Ogden, UT.

Project timeline

1
Scoping Start
10/07/2014
2
Decision
10/2014 (Estimated)
3
Implementation
11/2014 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Rocky Mountain Power Structure and Phase Raiser Maintenance PALS#45659Decision Signed Date: 10/17/2014
ForestsUinta-Wasatch-Cache National Forest
DistrictsOgden Ranger District
Legal Land DescriptionT7N,R1W Sec 25, 26 and T8N,R4E Sec 13,14,15,22,21,30 Salt Lake Base and Meridian
Special use management