USFS proposal to replace existing wooden vault toilet at the guard station with a new single seat toilet. This project is a pre-requisite to putting the Diamond Fork guard station into the rental system.
Location
T7S, R5E, Section 35
Project timeline
1
Scoping Start
12/02/2015
2
Decision
06/2016 (Estimated)
3
Implementation
06/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Facility Maintenance |
| Diamond Fork Guard Station toilet installation | Decision Signed Date: 06/03/2016 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Spanish Fork Ranger District |
| Legal Land Description | Not Applicable |