Decision Memo Completed

Hoy Hollow Pipeline

Uinta-Wasatch-Cache National Forest Wasatch, Utah Heber-Kamas Ranger District

Proposal to replace the existing headbox and connect it to a 1.5 inch polypipe. The pipe will be laid on the ground and will carry water to two troughs just outside of the Chevron pipeline corridor.

Location

On the slope to the north of the West Fork of the Duchesne near the eastern Forest Boundary

Project timeline

1
Scoping Start
09/30/2016
2
Decision
02/2017 (Estimated)
3
Implementation
05/2017 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (9), 36 Cfr 220.6(E)(9)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Structural Improvements
Hoy Hollow PipelineDecision Signed Date: 02/28/2017
ForestsUinta-Wasatch-Cache National Forest
DistrictsHeber-Kamas Ranger District
Legal Land DescriptionNot Applicable
Grazing management