Proposal to pave the two parking areas at the Echo picnic site and build a trail to the restroom. Proposal is intended to provide safer access between the two sites.
Location
American Fork Canyon, Echo picnic site below Tibble Fork Dam.
Project timeline
1
Scoping Start
10/14/2016
2
Decision
08/2017 (Estimated)
3
Implementation
09/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Echo Picnic Site Hardening | Decision Signed Date: 08/21/2017 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Pleasant Grove Ranger District |
| Legal Land Description | Not Applicable |