Proposal to replace and realign water infrastructure at the Weber Basin Job Corps Center by order of the State of Utah Division of Drinking Water, within its campus by Dec. 31, 2020. South Weber City will be implementing the project.
Location
Approximately 500%u2019 uphill (southeast) of Weber Basin Job Corps Campus, along dirt access road
Project timeline
1
Scoping Start
03/02/2020
2
Decision
05/2020 (Estimated)
3
Implementation
05/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| South Weber Water Transmission Line Replacement DM | Decision Signed Date: 05/07/2020 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Ogden Ranger District |
| Legal Land Description | Not Applicable |