Conduct stream enhancement treatments to be implemented within the identified 2,600 LF of Strawberry River mitigation area.
Location
T02S S15 R12W 30
Project timeline
1
Scoping Start
05/18/2020
2
Decision
06/2020 (Estimated)
3
Implementation
07/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Upper Strawberry UDOT mitigation restoration | Decision Signed Date: 06/23/2020 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Heber-Kamas Ranger District |
| Legal Land Description | Not Applicable |