Proposal from Salt Lake City Public Utilities to construct an additional storage reservoir at the existing Fort Douglas site.
Location
Mouth of Red Butte Canyon, east of University of Utah
Project timeline
1
Scoping Start
06/04/2020
2
Decision
06/2020 (Estimated)
3
Implementation
06/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Fort Douglas Storage Reservoir #2 Decision Memo | Decision Signed Date: 06/22/2020 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Salt Lake Ranger District |
| Legal Land Description | Not Applicable |