Decision Memo Completed

Tibble OHV Parking Lot

Uinta-Wasatch-Cache National Forest Utah, Utah Pleasant Grove Ranger District

Proposal to convert the recently disturbed borrow area just north of the current Tibble parking lot to a separate OHV parking lot. The area would be graded and road base would be applied.

Location

400 feet north of the current parking lot at Tibble Reservoir. Parking lot would be within the northern-most part of the disturbed area known as Borrow Pit %u201CA%u201D during the Tibble Reservoir Dam project in 2017.

Project timeline

1
Scoping Start
11/04/2020
2
Decision
12/2020 (Estimated)
3
Implementation
04/2021 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (5), 36 Cfr 220.6(D)(5); 32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDispersed Recreation Mgmt.; Trail Management
Tibble OHV Parking Lot Decision MemoDecision Signed Date: 12/03/2020
ForestsUinta-Wasatch-Cache National Forest
DistrictsPleasant Grove Ranger District
Legal Land DescriptionNot Applicable
Recreation management