Proposal to convert the recently disturbed borrow area just north of the current Tibble parking lot to a separate OHV parking lot. The area would be graded and road base would be applied.
Location
400 feet north of the current parking lot at Tibble Reservoir. Parking lot would be within the northern-most part of the disturbed area known as Borrow Pit %u201CA%u201D during the Tibble Reservoir Dam project in 2017.
Project timeline
1
Scoping Start
11/04/2020
2
Decision
12/2020 (Estimated)
3
Implementation
04/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5); 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Dispersed Recreation Mgmt.; Trail Management |
| Tibble OHV Parking Lot Decision Memo | Decision Signed Date: 12/03/2020 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Pleasant Grove Ranger District |
| Legal Land Description | Not Applicable |