Decision Memo Completed

Payson City New Buried Electric Transmission Line

Uinta-Wasatch-Cache National Forest Utah, Utah Uinta-Wasatch-Cache All Units

Payson City will construct a new buried 12.4 kV electric transmission line. Proposed right-of-way is approximately 2500 feet in length and 20 feet in width, along the Forest Boundary in section 21.

Location

Payson, UT. Base of the east slope of Little Mountain parallel to the Forest boundary and Goosenest Dr. for approximately 2,500 feet in length.

Project timeline

1
Scoping Start
04/29/2022
2
Decision
06/2022 (Estimated)
3
Implementation
07/2022 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission; Special Use Authorizations
Payson City New Buried Electric Transmission LineDecision Signed Date: 06/23/2022
ForestsUinta-Wasatch-Cache National Forest
DistrictsSpanish Fork Ranger District
Legal Land DescriptionT .9 S., R. 2 E., Sec 21
Special use management