Payson City will construct a new buried 12.4 kV electric transmission line. Proposed right-of-way is approximately 2500 feet in length and 20 feet in width, along the Forest Boundary in section 21.
Location
Payson, UT. Base of the east slope of Little Mountain parallel to the Forest boundary and Goosenest Dr. for approximately 2,500 feet in length.
Project timeline
1
Scoping Start
04/29/2022
2
Decision
06/2022 (Estimated)
3
Implementation
07/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Payson City New Buried Electric Transmission Line | Decision Signed Date: 06/23/2022 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Spanish Fork Ranger District |
| Legal Land Description | T .9 S., R. 2 E., Sec 21 |