Solitude proposes to improve its existing snowmaking infrastructure system through the expansion and improvement of Stilling Pond, the construction of two new snowmaking valve houses, the implementation of new snowmaking pipelines and coverage.
Location
Solitude Ski Resort
Project timeline
1
Scoping Start
08/11/2022
2
Decision
02/2023 (Estimated)
3
Implementation
06/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Solitude Snowmaking Project, Solitude Ski Resort | Decision Signed Date: 02/03/2023 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Salt Lake Ranger District |
| Legal Land Description | Not Applicable |