Decision Memo Completed

G Monument Rebuild

Uinta-Wasatch-Cache National Forest Utah, Utah Uinta-Wasatch-Cache All Units

Pleasant Grove City proposes to rebuild their G monument, which is in disrepair and is contributing to an impaired viewshed, soil erosion and unauthorized social trails. It's on the hillside east of town between Battle Creek and Grove Creek trails.

Location

Approximately 3/4 of a mile NE of the Battle Creek Trailhead on the Wasatch Front adjacent to Pleasant Grove.

Project timeline

1
Scoping Start
09/27/2022
2
Decision
09/2022 (Estimated)
3
Implementation
10/2022 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
G Monument RebuildDecision Signed Date: 09/30/2022
ForestsUinta-Wasatch-Cache National Forest
DistrictsPleasant Grove Ranger District
Legal Land DescriptionNot Applicable
Special use management