Proposed project is to repair and improve facilities at and adjacent to Pineview Trailhead and Port Ramp within existing recreation sites, make road improvements and connections, and to construct a new parking area.
Location
Project is located at/near Pineview Reservoir, Port Ramp, Pineview Trailhead, North Arm trailhead.
Project timeline
1
Scoping Start
02/01/2022
2
Decision
03/2023 (Estimated)
3
Implementation
06/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22); 32.2 (24), 36 Cfr 220.6(E)(24) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Trail Management |
| Pineview Reservoir Infrastructure Improvements | Decision Signed Date: 03/27/2023 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Ogden Ranger District |
| Legal Land Description | Township 6 North Range 1 East Sections 10 and 15 |